Overview
This project will replace water lines in four areas around the City of Arvada to maintain reliable water service. The work will take place in several locations, across several phases. Locations are as follows:
- Phase 1: 84th Way (Castle Gate Apartments) - in progress
- Between 84th Circle and Webster Drive
- Phase 2: 74th Place - in progress
- Between Kipling Street and 76th Drive
- Phase 3: Webster St. (south of Pamona Dr.) and W. 81st Ave. (east of Vance St.) - scheduled for March 2023
- A full closure of Webster and 81st Ave. will be necessary. Local resident access will be maintained.
- Phase 4: Routt to Robb Streets from W 59th Place to 60th Ave. - scheduled for April 2023
Timeline
*All work is weather and supply chain dependent and subject to change.
Phase 2
- Approximately 10 weeks
- Scheduled start date in February
- Completion anticipated in early April
Phase 3
- Approximately 2-3 weeks
- Scheduled start date in March
- Completion in early April
The timeline will be updated as the additional project phases are scheduled.
What to Expect
- Limited to no parking within construction zones
- No parking signs will be in place 24 hours before work begins
- Single lane closure with one-way traffic may take place throughout the project
- Flaggers and signage will be in place to direct traffic
- Scheduled water outages may occur
- Impacted residents will be notified with a door hanger from the contractor
- Slight, temporary water discoloration may result from water line connection
- The water is completely safe. Run your cold water faucet for several minutes until water returns to normal.
- Working hours will be between 7 a.m. to 7 p.m. on local, residential (neighborhood) streets.
- Working hours at 8:30 a.m. to 3:30 p.m. on major arterial and neighborhood collector roads.
- Additional construction traffic and noise may be present during these times
Contact
Please contact the Engineering Division with questions, (720) 898-7640 or submit a ticket through Ask Arvada and a team member will be in touch.