Indiana Street and 72nd Avenue Intersection Upgrade Project

  • Published
  • Updated
  • by Public Works

Beginning Monday, 9/24, a section of 72nd Ave. just west of Indiana will be closed for approximately 3 months for bridge construction. LOCAL access only will be permitted on 72nd Ave. between Quaker and Indiana Streets. View detour map below.

Beginning Tuesday, 9/25, a section of 72nd Ave. just east of Indiana will be closed for 4 days. View detour map below.

Read full press release for details

Detour map for 72nd Ave. WEST of Indiana

72nd Ave detour

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Detour map for 72nd Ave. EAST of Indiana

detour east 72nd Ave

 

General Progress Update - week of September 23: Work on both Indiana Street and 72nd Avenue continues this week with single-lane, alternating traffic utilizing flaggers (Monday - Friday, 8:30 a.m. to 3:30 p.m.). Crews will install sidewalk and place asphalt on the east side of the corridor. Utility relocation work continues. Please Note: All businesses are open during construction.

What to Expect

The City of Arvada and contractor partner, Jalisco International, are beginning a year-long project to widen the intersection of Indiana Street (Colorado Highway 72) and 72nd Avenue. 

Indiana Street and 72nd Avenue--Currently

  • Intermittent lane closures with alternating traffic from 8:30 a.m. to 3:30 p.m., Monday through Friday.
  • One lane in each direction will be provided whenever possible during working hours and when work is not taking place.
  • Occasional night and weekend work is expected.
  • Speed limit reductions are anticipated and fines are double within work zone. 
  • The project is weather-dependent and the schedule is subject to change. 

Project completion is expected in summer 2019.

Project Overview

Plans to improve the intersection have been in development since 2013. This $7-million project is funded through the City’s Capital Improvement Project Fund. Planned intersection enhancements will improve the safety and functionality of the intersection. This project will raise the profile of the roadway to improve drainage, upgrade the traffic signal and provide additional capacity through the intersection. The  new intersection layout has been designed to accommodate future traffic volumes. Two lanes in each direction will be provided through the intersection and Indiana Street will be widened to accommodate double left-turn lanes in both directions. Other project improvements include:

  • New sidewalks and on-street bike lanes
  • Undergrounding utilities
  • Water line replacement
  • Storm sewer upgrades
  • Bridge expansion on 72nd Avenue over Croke Canal

Contact

Project hotline: 720-900-8670; project email: indiana72nd@workzone.info.

To be added to the project notification list for future project updates, send a request to the indiana72nd@workzone.info.