Project Description

During the morning peak hours, the western leg of W 82nd Avenue at Indiana Street intersection sees a backup of eastbound traffic occasionally blocking access to the right turn lane. To improve this congestion, the City is lengthening the eastbound right turn lane on 82nd Avenue approximately 250 feet. The proposed widening will be accompanied by striping revisions to extend the eastbound left turn lane and potential signal timing improvements to further alleviate morning congestion.

Tentative Timeline

90% Review meeting = May 2020
Design Complete = July 2020
Construction = This project will be included in the 2021 Asphalt Program. While the specific project has not been scheduled, the Asphalt Program typically begins in the spring of each year. 

Questions?

Email pw_workzone@arvada.org