64th Ave. and Indiana Street

  • Published
  • Updated
  • by City Manager
  • 2926 Views
Beginning Wednesday, May 31, road work will commence at the W. 64th Ave. and Indiana Street intersection. Work will take place between the hours of 8:30 a.m. and 3:30 p.m. Monday through Friday. Construction includes the installation of:
 
  • an additional left turn lane on eastbound W. 64th Ave. at Indiana Street
  • a 700 foot acceleration lane on northbound Indiana Street
  • ADA ramps
  • curb and gutter
  • asphalt installation
  • signing and striping
  • other miscellaneous work
The project is anticipated to be completed by Friday, July 14.
 
Expect lane closures on W. 64th Avenue and Indiana Street. Please use caution in the construction area and consider alternate routes to avoid traffic delays.
 
road work map at 64th and Indiana